MNB Architects
Sunday, November 19, 2017

Project Schedule

 
Preliminary Project Schedule
 
Programming Phase

45 Days

Owner’s Approval of Program 15 Days
Schematic Design Phase 30 Days
Owner’s Approval of Schematic Design Phase  15 Days
   
Design Development Phase 45 Days
Owner’s Approval of Design Development Phase  15 Days
   
   
Submission to Town for Planning Commission, Design Review 
Commission and Board of Mayor and Aldermen
90 Days
 
(To run concurrently with Design Development and Construction Document Phases)
 
Construction Document Phase 75 Days
Owner’s Approval of Construction Document Phase 15 Days
Bidding and Negotiation Phase 45 Days
Owner’s Approval of Bidding 
(including contract execution)
 30 Days
   
Construction Administration 12 Months
Project Closeout and Owner’s Acceptance of Project  30 Days