Project Schedule
Preliminary Project Schedule
Programming Phase |
45 Days
|
Owner’s Approval of Program |
15 Days |
Schematic Design Phase |
30 Days |
Owner’s Approval of Schematic Design Phase |
15 Days |
|
|
Design Development Phase |
45 Days |
Owner’s Approval of Design Development Phase |
15 Days |
|
|
|
|
Submission to Town for Planning Commission, Design Review
Commission and Board of Mayor and Aldermen |
90 Days |
|
(To run concurrently with Design Development and Construction Document Phases)
|
Construction Document Phase |
75 Days |
Owner’s Approval of Construction Document Phase |
15 Days |
Bidding and Negotiation Phase |
45 Days |
Owner’s Approval of Bidding
(including contract execution) |
30 Days |
|
|
Construction Administration |
12 Months |
Project Closeout and Owner’s Acceptance of Project |
30 Days |
|
|